Daubert Standard For Takt

The Daubert standard, named after the legal case Daubert v. Merrell Dow Pharmaceuticals, Inc. (1993), is a criterion used by courts in the United States to assess the admissibility of expert witness testimony. This standard replaced the Frye standard, which focused mainly on the general acceptance of scientific methods within a particular field.
Under the Daubert standard, when a court is presented with expert testimony, it must evaluate whether the expert’s methods and reasoning are scientifically valid and reliable. The court considers factors such as whether the expert’s theory or technique can be tested, whether it has been subjected to peer review and publication, its error rate, and whether it is generally accepted within the scientific community.
In the context of forensic analysis, such as in scheduling cases, the Daubert standard requires that the methods used by forensic experts in analyzing schedules must be scientifically valid and reliable. This might involve demonstrating that the techniques used to analyze schedules, such as algorithms or statistical methods, have been rigorously tested, are subject to peer review, and have an acceptable error rate. Additionally, the expert may need to show that these methods are generally accepted within the forensic analysis community. If the court determines that the methods used by the expert meet these criteria, the expert testimony may be deemed admissible. Otherwise, it may be excluded.
The Daubert standard outlines several criteria that courts consider when determining the admissibility of expert testimony. These criteria include:
Overall, the Daubert standard aims to ensure that expert testimony is based on reliable scientific principles and methods, rather than subjective opinions or speculation. Courts use these criteria to assess the reliability and validity of expert testimony to make well-informed decisions about its admissibility in legal proceedings.
We have created standards for the Takt Production System® where possible to enable TPS® to eventually allow Takt planning to be used in court cases in lieu of CPM.

Takt Overview in Summary

Takt planning is the ideal First Planner System. It is a planning method that brings flow to the project. Additionally, it prepares work for Last Planner® and Scrum by queueing work up for those systems with workflow, trade flow, and logistical flow. It is effective in doing this because the plan is crafted early on when information, material, and manpower procurement can align with the flow and sequence.
A Takt plan is
It is the only scheduling system that shows all three types of flow—
Flow is identified by evaluating the schedule’s—
And the structure not only enables, but almost forces the user to obey four key production laws—
Which results in—
Takt Integrity Checklist
We have also been asked to provide a quick integrity checklist to remind project teams of the requirements they must meet to have completed a Takt plan that is whole. This list is also included in the Takt Excel template.
Does my Takt plan…
Meet the following requirements…
Does my Takt plan…
Comply with my Takt Schedule Health Metrics…
Does my Takt plan…
Have a solid…
Does my Takt plan…
Obey…
Does my Takt plan…
Enable you to…
We hope this checklist has been helpful in deciding if your Takt plan is whole and serving you well.